Illustrative bar chart of SMED stages: a long changeover with mixed internal and external work, then separating them, converting internal work to external, and streamlining what remains
Guide

SMED: How to Cut Changeover Time Step by Step

SMED (Single-Minute Exchange of Die) is the classic method for shortening changeovers. Developed by Shigeo Shingo, it rests on one idea: do as much setup work as possible while the machine is still running. This guide explains the stages, how to run a first SMED workshop from a filmed changeover, and how to keep the new time from creeping back.

What SMED means

SMED stands for Single-Minute Exchange of Die. "Single-minute" means a changeover that takes a single-digit number of minutes, so under ten. The name comes from press shops, where a changeover meant swapping a die, but the method applies to any switch from one product to the next: moulds, fixtures, filler formats, recipes, even software configurations.

The Lean Enterprise Institute describes the core of Shigeo Shingo's approach as separating internal setup operations, which can only be done when a machine is stopped (such as inserting a new die), from external operations that can be done while it is running (such as bringing the new die to the machine), and then converting internal operations into external ones. Shingo documented the method in his 1985 book A Revolution in Manufacturing: The SMED System.

Why changeover time matters

A changeover is time the asset is planned to run but produces nothing saleable. In OEE terms it is an Availability loss (see How to Calculate OEE). Long changeovers also push planners toward large batches, which means more inventory, longer lead times and slower response to customers. Shorter changeovers make smaller batches economical, which is why SMED is a foundation for flow and pull.

The SMED Changeover Calculator lets you list changeover elements, mark them internal or external, and see the time you would recover by converting them.

The SMED stages

Stage 0: Observe the current changeover

Before changing anything, record a real changeover from the last good part of product A to the first good part of product B. Include the hunt for tools, the paperwork and the trial runs; they are part of the changeover even if nobody thinks of them that way.

Stage 1: Separate internal and external work

Go through every element and ask: does the machine have to be stopped to do this? Fetching tools, finding the next material, pre-heating and checking the next fixture usually do not. Simply moving these before or after the stoppage, with a checklist, often gives a large reduction with no investment.

Stage 2: Convert internal work to external

Next, look at the remaining internal elements and ask how they could be done while the machine runs. Typical examples are pre-heating a mould, pre-assembling a fixture on a second base plate, or pre-setting tools off-line to a known dimension.

Stage 3: Streamline everything

Finally, shorten what remains. Replace bolts with quick clamps or quarter-turn fasteners, standardize fastener sizes so one tool fits all, use locating pins so parts go in the right place first time, eliminate adjustments with fixed stops, and run parallel tasks with two people where it is safe. Then streamline the external work too, because it still consumes labour.

Five steps of a first SMED workshop: pick one changeover, film and list tasks, mark each internal or external, move work to external, streamline and standardize
A first SMED workshop usually follows this path, using a video of a real changeover.

Running your first SMED workshop

  1. Choose the changeover. Pick one that is frequent, long, or on a constraint. A changeover on the bottleneck is worth more than the same minutes saved elsewhere.
  2. Film it. One camera on the operator, one on the machine if possible. Tell the team why you are filming; it is about the method, not the person.
  3. Break it into elements. From the video, list every step with its start and end time and the distance walked.
  4. Classify and challenge. Mark each element internal or external, then challenge each internal element with "what would it take to do this while running?"
  5. Try it. Rehearse the new sequence on the next real changeover, measure it, and adjust.
  6. Standardize. Write the new sequence as a one-page standard with photos, kit the tools on a cart, and train every shift.

When several products share a machine, the order in which you run them also affects total changeover time. The Changeover Matrix and Sequencing Helper helps you find a lower-loss product sequence once individual changeovers are under control.

Video: SMED: How to do a Quick Changeover by LeanVlog (YouTube). Click to play; nothing loads from YouTube until you do.

Measuring a changeover properly

LEI defines changeover time as the time elapsed between the last piece in the run just completed and the first good piece from the process after the changeover. That definition counts the slow start-up and the scrap that a "tool change finished" timestamp would hide. Track it on a simple run chart per machine; the trend shows whether the new standard is holding.

A worked example of the logic

Suppose a filmed changeover lists twelve elements. Four of them, fetching the next mould, finding the right clamps, pre-heating the mould and collecting the first-off inspection sheet, are currently done with the machine stopped but do not need to be. Moving them before the stop, with a checklist and a pre-staged cart, removes their time from the changeover entirely. Two more elements, setting the mould height and centring it, can be converted to external work with a standard-height sub-plate and locating rings prepared off-line. The remaining internal elements are then streamlined with quick clamps and fixed stops so no trial-and-adjust cycles are needed.

The exact gain depends entirely on your process; the point of the example is the order of work. Do the free reorganisation first, then the low-cost conversions, and only then spend money on hardware, because by that stage you know exactly which elements are worth investing in.

Making the new standard stick

  • Changeover cart: every tool and part needed, in a marked home, checked before the stop.
  • One-page standard: the sequence with photos and who does what if two people work in parallel.
  • Pre-changeover checklist: confirms external tasks are done before the machine stops.
  • Run chart at the machine: every changeover time recorded and reviewed in the daily meeting.
  • Repeat the workshop: after the new time is stable, film again and look for the next round of improvements.

Common pitfalls

  • Skipping Stage 1. Teams jump to buying quick-release hardware before organising the free improvements.
  • Ignoring adjustments. Trial-and-adjust cycles at start-up are often the longest element; fixed settings and locators remove them.
  • No standard afterwards. Without a written method and a tool cart, each shift slowly reverts to its own way.
  • Not using the time gained. If shorter changeovers are not turned into smaller batches or more capacity, the benefit stays on paper.

Where SMED fits with TPM and OEE

SMED attacks changeover time, which LEI lists among the six major losses that Total Productive Maintenance targets (downtime, changeover time, minor stops, speed losses, scrap and rework). It works best alongside autonomous maintenance and 5S, because a clean, organised machine with labelled settings is far easier to change over. If you are building a wider loss-reduction programme, the TPM 8 Pillars article shows where it fits.

Related free tools

Sources and further reading

Frequently asked questions

What does SMED stand for?
Single-Minute Exchange of Die: a changeover method aiming for changeovers in single-digit minutes (under ten), developed by Shigeo Shingo.
What is the difference between internal and external setup?
Internal setup can only be done when the machine is stopped. External setup can be done while it is still running, such as preparing tools and materials for the next job.
How do you measure changeover time?
The Lean Enterprise Institute measures it from the last piece of the completed run to the first good piece after the changeover, so start-up adjustments and scrap are included.
Can SMED be used outside manufacturing?
Yes. The same logic applies to any switch between jobs, such as operating theatre turnover, aircraft turnaround or switching a line between recipes.